The EIA is the floor, not the ceiling.

Written by
James Rogers Jones
Published on
noviembre 10, 2026

Key takeaways

  • Public opposition has hit around $42bn of European data centre investment through delays and cancellations.
  • Land, water and energy are the concerns communities raise most, and an EIA is built to assess all three.
  • Starting the EIA early lets you test and refine the design while changes are still cheap.
  • Scotland requires an EIA above 50MW of power capacity. England’s draft National Policy Statement uses 100MW of IT load. The UK needs one rule.
  • An EIA is built to find risk. The baseline data behind it also shows where a project can give something back.
  • Plain language and honest conversations turn a technical document into community trust.

Why data centres face growing local opposition

When a new data centre is proposed, people living nearby want to know what it will mean for them. Will it put pressure on local power supplies and water resources? What happens to the surrounding land and green space? And what will the community get in return?

These are reasonable questions, but too often they go unanswered. The consequences are becoming increasingly clear, with public opposition estimated to have put around $42bn of data centre investment in Europe at risk through delays and cancellations. In the US, the figure is closer to $77bn.

An Environmental Impact Assessment (EIA) is one of the key ways developers can address these concerns. It assesses how a project will affect its surroundings, from land, water and energy use to ecology and local communities. Yet we should be looking at it as more than a planning requirement. Done properly, an EIA can help us design better projects and build the trust needed to deliver them.

The cost of getting it wrong

We're already seeing projects face delays because environmental considerations haven't been properly addressed. In Edinburgh, a proposed Hyperscale data centre is on hold until the developer submits an EIA. In Finland, Google was ordered to stop work at two sites after clearing forest without one.

Regulation is also moving in this direction. Scotland now requires an EIA for data centres above 50MW of power capacity. In England, the draft National Policy Statement sets a 100MW IT load threshold for projects using the national infrastructure planning route, with a full EIA required.

Both are steps forward, but the difference in thresholds highlights the need for a more consistent approach across the UK. For developers, understanding and addressing environmental impacts should be part of project planning from the outset, not something we come back to when challenges arise.

Start with the EIA, not the planning application

Our view is simple: an EIA should be one of the first steps in developing a data centre, not a report commissioned once the design is already taking shape.

Starting early allows us to use the findings to influence decisions while there is still room to make changes. We can test different site layouts, cooling strategies, access arrangements and environmental mitigation measures before they become expensive to change. It also means we can identify potential concerns and have more informed conversations with local authorities and communities before positions become entrenched.

Ultimately, an EIA is a form of risk management. The earlier we understand the risks, the more opportunities we have to address them.

Beyond planning permission: what should communities get in return?

Two recent cases show why community trust matters. In April, Leeds City Council granted planning permission for Microsoft's campus at Skelton Grange, yet a petition against the development has attracted more than 42,000 signatures. In North Wales, a proposed AI data centre beside the Menai Strait has drawn more than 22,000 signatures while its future remains undecided. One has planning consent, the other is still waiting, but both show that planning permission doesn't necessarily mean community support.

As EIAs become a baseline requirement, another question becomes increasingly important: what should a community expect in return for hosting a data centre?

Data centres are essential to the digital economy, but they also place significant demands on local land, power and water resources. The people living nearby don't necessarily experience the digital benefits these facilities enable. So how can we make that exchange more balanced?

An EIA helps us understand potential impacts, but its findings can also highlight opportunities to create something positive. We need to ask not just what could go wrong, but what could go right, and for whom? That might mean using waste heat to warm a local leisure centre, creating apprenticeships or investing in woodland that will benefit the area for decades.

Permanence is the real test. Communities remember lasting assets far longer than announcements made during consultation. Commitments need to be properly planned, costed and maintained, with a clear purpose and owner long after construction ends.

Just as importantly, we need to communicate these commitments in a way people can understand. An EIA can run to hundreds of pages, but translating its findings into plain language, clear visuals and honest conversations is what helps communities understand both the challenges and the opportunities.

Every data centre will need to demonstrate its environmental impact. The developers who go further and demonstrate their value to the community will be better placed to earn long-term support.

Our Sustainable Development team helps developers turn EIA evidence into better design decisions and meaningful community commitments. Talk to our team to get started.

‍

‍

Join our mail list!
Get updates on events and insights, no spam
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Get your free report
Leave your details to read this report.
Thank you! Your report should be downloaded.
Oops! Something went wrong while submitting the form.